| Complete Policy Title: | PREPAYMENT POLICY FOR NON-TRAVEL RELATED EXPENSES |
| Policy Number (if applicable): | P-150 |
| Approved by: | COG |
| Date of Most Recent Approval: | October, 1996 |
| Revision Date(s): | |
| Position Responsible for Developing and Maintaining the Policy: | Director, Purchasing Resources |
| Contact Department: | PURCHASING RESOURCES |
| DISCLAIMER: | If there is a discrepancy between this electronic policy and the written copy held by the Policy owner, the written copy prevails. |
It is the policy of the Purchasing Department to process prepayments only if it is proven necessary to secure goods and/or services required to facilitate the University's day-to-day operations.
This procedure applies to all Purchasing Resources employees.
Occasionally, a supplier may require a prepayment or a
downpayment for a number of different reasons, eg. first-time supplier,
goods being shipped from another country, supplier's cash flow requirement,
etc. Since the University may be losing interest income by processing
prepayments, these situations should be the exception and therefore should
be avoided if possible. Prepayments can be processed for a purchase order
via a cheque requisition in accordance with the cheque requisition policy.
For further information, refer to "Cheque Requisition Policy AP-030".
Prepayments via cheque requisitions must be initiated by the
originator of the cheque requisition and in accordance with the "Cheque
Requisition Policy AP-030".
Prepayments covering a purchase order must be processed via a
cheque requisition that is initiated and authorised by the applicable
Purchasing Officer within his/her delegated signing authority.
In order to process a prepayment, the purchase order
and the cheque requisition must be accompanied by: an original invoice,
a proforma invoice, or the original order list.